Elektromontaż Wschód as a general contractor is involved in the construction of 110/15 kV substations in Reptowo for railways under the government program MUZA III and MUZA IV.

The scope of work includes:

  • construction of a 110kV power line input equipped with a three-pole circuit breaker,
  • construction of a 110kV transformer bay,
  • construction of a power transformer station,
  • delivery, assembly and commissioning of a power transformer,
  • construction of the station, assembly, connection and commissioning of the grounding transformer,
  • construction of the station, assembly, connection and commissioning of the transformer for own needs,
  • delivery, assembly and commissioning of 15kV switchgear,
  • delivery, assembly and start-up of 3kV DC switchgear,
  • the construction of a 110kV cable line of traction substation Reptowo – GPZ Morzyczyn with an optical fibre line,
  • the construction of the 110kV bay in Morzyczyn in terms of foundations and construction for heads, overvoltage limiter and disconnector,
  • supply, assembly and commissioning of the switchgear for own needs,
  • execution of the technical protection system,
  • the assembly of lightning masts with the implementation of the grounding system,
  • construction of cable ducts,
  • execution of LV installation,
  • execution of sanitary installations, water connections,
  • construction of roads, station fencing with a soundproofing screen panel,
  • as-built documentation.

Share

See more

GPZ Bielin i GPZ Chojna
Energy infrastructure

GPZ Bielin and GPZ Chojna

Elmont, commissioned by Enea Operator, will carry out a comprehensive modernization of two 110/15 kV power stations in the West Pomeranian Voivodeship – GPZ Bielin

Energy infrastructure

110/15 kV GPZ Piątek

Alongside investments in renewable energy sources, Elmont is carrying out strategic infrastructure projects for the Distribution System Operator (DSO).One of these projects is the construction

Photovoltaic farms

18 Photovoltaic Farms 30MW

Elmont, as the general contractor, is starting the implementation of a large photovoltaic investment in western Poland.As part of the project, photovoltaic farms with capacities

Energy infrastructure

RS 110kV 10 months ahead of schedule!

Elmont, commissioned by PGE, has successfully completed the construction of a 110 kV network switchboard for the connection of the Lipińskie Małe Traction Substation. The

See our projects

OZE energia odnawialna, energetyka Elmont Grupa
Scroll to Top
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.