Rebuilding of the HV / MV station in Czarna Białostocka

Elmont Grupa – Infrastruktura Energetyczna

Elektromontaż Wschód has rebuilt the 110/6 kV station in Czarna Białostocka.

The scope of works included:

  • the demolition of existing buildings, structures and equipment in accordance with technical documentation and demolition permit,
  • the construction and assembly works in accordance with technical documentation and building permit,
  • the assembly and commissioning of all devices provided for in the project,
  • the execution of a complete station telemechanics system in accordance with technical documentation, including the delivery of materials and devices and all related configuration and commissioning works,
  • entering the settings into the built-in devices and carrying out the commissioning checks of all equipped switchgear bays in accordance with the approved commissioning program and their confirmation with protocols,
  • performing tests and functional tests of the entire telemechanics system, including communication with the local and central BTC PRINS dispatcher supervision system and in the engineering supervision channel,
  • the development of as-built documentation,
  • the development and approval of the Station Operation Manual by the Operator.

Share

See more

Wind farms

6,6 MW Wind Farm

Elmont will execute the Chrośle Wind Farm project with a capacity of 6.6 MW. The scope of work includes the construction of a MV cable

Energy infrastructure

Construction of RS 110 kV Lipińskie Małe

Elmont, on behalf of PGE, has commenced the construction of a 110 kV network substation for the connection of the Lipińskie Małe Traction Substation. The

RS Augustynka - Elmont
Energy infrastructure

RS 110 kV for PV 25MW Augustynka

Elmont, commissioned by PGE, completed the construction of a 110 kV network switchgear for the purpose of connecting the Augustynka photovoltaic farm with a total