6,6 MW Wind Farm

Elmont will execute the Chrośle Wind Farm project with a capacity of 6.6 MW.

The scope of work includes the construction of a MV cable line connecting the Chrośle substation to the Nowe Miasto Lubawskie substation, spanning 13 km, as well as a station building for three wind turbines, each with a capacity of 2.2 MW.

The planned completion date for the project is June 2025.

Share

See more

Energy infrastructure

RS 110kV 10 months ahead of schedule!

Elmont, commissioned by PGE, has successfully completed the construction of a 110 kV network switchboard for the connection of the Lipińskie Małe Traction Substation. The

Energy infrastructure

Construction of RS 110 kV Lipińskie Małe

Elmont, on behalf of PGE, has commenced the construction of a 110 kV network substation for the connection of the Lipińskie Małe Traction Substation. The

RS Augustynka - Elmont
Energy infrastructure

RS 110 kV for PV 25MW Augustynka

Elmont, commissioned by PGE, completed the construction of a 110 kV network switchgear for the purpose of connecting the Augustynka photovoltaic farm with a total

See our projects

OZE energia odnawialna, energetyka Elmont Grupa
Scroll to Top