The Elmont will build a 40 MW photovoltaic farm in the Chotków turnkey formula for a foreign investor.
As part of the project, electricity will be led out of the farm via a 30 kV cable connection to the GPO 110/30kV Chotków substation we are building.
The photovoltaic power plant under construction will contain a total of over 61,000 modules, each with a power of 650 Wp, arranged on tables in a vertical arrangement on metal supporting structures.
The deadline for commissioning the investment is the second quarter of 2023.