The wind farm in Gostynin is being built on schedule. So far, we have already built a MV cable line, fiber optic line as well as the RSN switching station. Road works are underway. And a few days ago, the first 2MW wind turbine was delivered. The delivery of turbines is a huge logistical challenge each time due to their dimensions.
![](https://elmontgrupa.pl/wp-content/uploads/2024/06/zdjecia-na-bloga-2.jpg)
Energy infrastructure
Construction of RS 110 kV Lipińskie Małe
Elmont, on behalf of PGE, has commenced the construction of a 110 kV network substation for the connection of the Lipińskie Małe Traction Substation. The