Double-circuit 110kV overhead line for TAURON

Elmont Grupa – Infrastruktura Energetyczna

At the request of TAURON, Elektromontaż Wschód will rebuild the double-circuit 110 kV overhead line into single-track lines (overhead and underground) from the pylons to the Ząbkowice GPZ.

The scope of work includes:

a) reconstruction of the 110 kV S-293 overhead line,

b) reconstruction of the 110 kV S-208 overhead line, including the construction of a pylon,

c) construction of a 110kV cable line,

d) construction of optical fibre line.

Share

See more

Energy infrastructure

RS 110kV 10 months ahead of schedule!

Elmont, commissioned by PGE, has successfully completed the construction of a 110 kV network switchboard for the connection of the Lipińskie Małe Traction Substation. The

Wind farms

6,6 MW Wind Farm

Elmont will execute the Chrośle Wind Farm project with a capacity of 6.6 MW. The scope of work includes the construction of a MV cable

Energy infrastructure

Construction of RS 110 kV Lipińskie Małe

Elmont, on behalf of PGE, has commenced the construction of a 110 kV network substation for the connection of the Lipińskie Małe Traction Substation. The

RS Augustynka - Elmont
Energy infrastructure

RS 110 kV for PV 25MW Augustynka

Elmont, commissioned by PGE, completed the construction of a 110 kV network switchgear for the purpose of connecting the Augustynka photovoltaic farm with a total

See our projects

OZE energia odnawialna, energetyka Elmont Grupa
Scroll to Top