Substation 400kV Łomża Systemowa PSE

Elmont Grupa – Infrastruktura Energetyczna

On behalf of Polskie Sieci Elektroenergetyczne S.A. Elektromontaż Wschód deals with the removal of errors and modernization of the Substation Łomża Systemowa, which was implemented as part of the “Poland-Lithuania power connection” project.

The scope of work includes primary and secondary circuits as well as general construction works.

The implementation period is 18.03 – 18.12.2021.

The choice of Elektromontaż Wschód as the contractor for the project was influenced by our image of a proven professional who can be entrusted with the implementation of the most demanding and advanced engineering works.

Share

See more

Enea Smart Grid - Elmont - infrastruktura energetyczna
Energy infrastructure

SMART GRID for ENEA

Commissioned by ENEA Operator sp. z o.o., Elmont built a Smart Power Grid in Szczecin, Gryfino district and Świnoujście. The investment included the modernization and

See our projects

OZE energia odnawialna, energetyka Elmont Grupa