Wind Farm Banie III 81,4 MW

Elmont Grupa – Farmy Wiatrowe

On the order of the investor of the Banie III wind farm, Elektromontaż Wschód will build a 110 kV power section.

The scope of work includes the development of substitute technical documentation and detailed design, comprehensive construction of a 15 / 110kV power station with 110kV cable connections, SCADA system, commissioning and putting into use.

Share

See more

Energy infrastructure

RS 110kV 10 months ahead of schedule!

Elmont, commissioned by PGE, has successfully completed the construction of a 110 kV network switchboard for the connection of the Lipińskie Małe Traction Substation. The

Wind farms

6,6 MW Wind Farm

Elmont will execute the Chrośle Wind Farm project with a capacity of 6.6 MW. The scope of work includes the construction of a MV cable

Energy infrastructure

Construction of RS 110 kV Lipińskie Małe

Elmont, on behalf of PGE, has commenced the construction of a 110 kV network substation for the connection of the Lipińskie Małe Traction Substation. The

RS Augustynka - Elmont
Energy infrastructure

RS 110 kV for PV 25MW Augustynka

Elmont, commissioned by PGE, completed the construction of a 110 kV network switchgear for the purpose of connecting the Augustynka photovoltaic farm with a total

See our projects

OZE energia odnawialna, energetyka Elmont Grupa
Scroll to Top