Modernization of the Main Supply Point Stargard

Elmont Grupa – Infrastruktura Energetyczna

On behalf of Enea, Elektromontaż Wschód, as the general contractor, deals with the modernization of the Stargrad Main Supply Point station.

The scope of work includes:

  • the disassembly and construction of the new Morzyczyn-Kluczewo power line input,
  • the disassembly and construction of a new Morzyczyn I power line input,
  • checking and commissioning of the Morzyczyn-Kluczewo, Morzyczyn I bays,
  • the disassembly of the old stand and TR2 bay,
  • the installation of new TR2 bay,
  • voltage supply to the TR2 bay,
  • the construction works in the building,
  • the installation of lightning protection and grounding,
  • sanitary installation,
  • voltage supply to the newly built power line inputs: Morzyczyn-Kluczewo, PKP No. 2, Morzyczyn I and the transformer bay TR 2,
  • construction works in the control room building,
  • telemechanics,
  • external lighting,
  • Technical Protection System.
Elmont Grupa – Infrastruktura Energetyczna
Elmont Grupa – Infrastruktura Energetyczna

Share

See more

Energy infrastructure

Construction of RS 110 kV Lipińskie Małe

Elmont, on behalf of PGE, has commenced the construction of a 110 kV network substation for the connection of the Lipińskie Małe Traction Substation. The

RS Augustynka - Elmont
Energy infrastructure

RS 110 kV for PV 25MW Augustynka

Elmont, commissioned by PGE, completed the construction of a 110 kV network switchgear for the purpose of connecting the Augustynka photovoltaic farm with a total

Farma fotowoltaiczna
Photovoltaic farms

A 40MW photovoltaic farm in western Poland

Elmont, commissioned by a foreign investor, started the construction of a turnkey photovoltaic farm with a capacity of 40 MWp in western Poland. The farm

See our projects

OZE energia odnawialna, energetyka Elmont Grupa
Scroll to Top