Modernization of the MV switching station of the 110/15 kV Nida

Elmont Grupa – Infrastruktura Energetyczna

Ordering party: PGE Dystrybucja S.A.

Period of implementation: 2014

Scope of works:

  • execution of construction and assembly works,
  • configuring and starting the protection relay communication,
  • calculating and entering the settings into the protection relay,
  • carrying out functional tests of telemechanics from the local level and from the central dispatch supervision system and the communication in the engineering supervision channel,
  • the updating of existing Station Operating Instructions and diagrams,
  • basic works related to the changes introduced at the stations.

Share

See more

Energy infrastructure

Construction of RS 110 kV Lipińskie Małe

Elmont, on behalf of PGE, has commenced the construction of a 110 kV network substation for the connection of the Lipińskie Małe Traction Substation. The

RS Augustynka - Elmont
Energy infrastructure

RS 110 kV for PV 25MW Augustynka

Elmont, commissioned by PGE, completed the construction of a 110 kV network switchgear for the purpose of connecting the Augustynka photovoltaic farm with a total

Farma fotowoltaiczna
Photovoltaic farms

A 40MW photovoltaic farm in western Poland

Elmont, commissioned by a foreign investor, started the construction of a turnkey photovoltaic farm with a capacity of 40 MWp in western Poland. The farm