Elektromontaż Wschód, as a general contractor, has completed the works covering the design, construction and commissioning of auxiliary stations equipped with automatic follow-up compensation at the 110 / 15kV Kotuń station and replacement of compensation units at the Łuków station.
The scope of works included the :
- modernization of MV 15kV stations and bays for own needs,
- installation of new compensation chokes, transformers and resistors at auxiliary stations,
- retrofitting auxiliary bays in the 15 kV switchgear with regulators of follow-up compensation systems.
Two fields at the stations in Kotuń and Łuków.