Modernization of the Traction Substation Mienia and Sosnowe

Elektromontaż Wschód until December 2018 modernized PT Mienia and PT Sosnowe Traction Substations. The works were commissioned by PKP Energetyka.

The scope of work included:

  • the development of complete design documentation with its necessary arrangements,
  • the execution of modernization works in the scope of replacement of ABB production safety devices with C&C production safety devices with adjustment of cabinets with the requirements of the Ordering Party,
  • the replacement of short-circuit protections of the RIs-10 rectifier to uUTXvL,
  • the replacement of current transformers on 1.3kV bridges,
  • as-built measurements,
  • starting the system,
  • as-build documentation.

Share

See more

Energy infrastructure

New GIS 110kV for EON

Consortium of companies Elmont Sp. z o. o. and Pracownia Projektowa Enspro Sp. z o. o. will develop executive documentation and build a 110 kV

Photovoltaic farms

Photovoltaic farms with a total capacity 4MW

Elmont, together with Pracownia Projektowa Enspro, will design and build photovoltaic farms with a total capacity of 4 MW.The scope of work includes the preparation