The equipping of the Legionowo HV / MV station with a telemechanics facility controller

Elmont Grupa – Infrastruktura Energetyczna

The equipping of the Legionowo HV / MV station with a telemechanics object controller with reference to the station circuits, activation of connections and communication with the dispatching system.

Ordering party: PGE Dystrybucja S.A.

Period of implementation: 2014

Scope of works:

  • the development of executive documentation for replacement of protections in 110kV switching station,
  • the replacement of protections of the 15kV switchgear and the facility telemechanics of the 110/15 kV Legionowo station,
  • the replacement of protections in 30 bays of 15kV switchgear with digital relays,
  • comprehensive replacement of secondary circuits in 30 bays of 15kV switchgear,
  • performance of configuration and start-up works on new protection relays,
  • exchange of protections in 7 bays of 110 kV switching station,
  • the performance of configuration and start-up works on new protection relays,
  • delivery, assembly and commissioning of the SO-55 telemechanics controller,
  • the execution of complete station telemechanics system with delivery of all materials and devices,
  • configuration and start-up works of the new telemechanics system,
  • development of as-built documentation.

Share

See more

Energy infrastructure

110/15 kV GPZ Piątek

Alongside investments in renewable energy sources, Elmont is carrying out strategic infrastructure projects for the Distribution System Operator (DSO).One of these projects is the construction

Photovoltaic farms

18 Photovoltaic Farms 30MW

Elmont, as the general contractor, is starting the implementation of a large photovoltaic investment in western Poland.As part of the project, photovoltaic farms with capacities

Energy infrastructure

RS 110kV 10 months ahead of schedule!

Elmont, commissioned by PGE, has successfully completed the construction of a 110 kV network switchboard for the connection of the Lipińskie Małe Traction Substation. The

Wind farms

6,6 MW Wind Farm

Elmont will execute the Chrośle Wind Farm project with a capacity of 6.6 MW. The scope of work includes the construction of a MV cable