Elmont, commissioned by PGE, completed the construction of a 110 kV network switchgear for the purpose of connecting the Augustynka photovoltaic farm with a total connection capacity of 25MW within the contractual deadline.
The first stage of work included technical documentation and the construction of the RS-110 kV Augustynka network switching station with accompanying infrastructure (station building, cable ducting, internal roads, exits, fencing, and the MV switching station for own needs).
The 110 kV overhead switchgear was built in a two-section H2 system with a single busbar system, with circuit breakers in the line bays, and with current and voltage transformers in the line bays. The clutch connector field is equipped with disconnectors.
The second stage involved the development of an executive design covering the connection of the HV-110 kV line from GPZ Milejczyce – GPZ Adamowo with the RS Augustynka 1 network switchboard in order to connect the Augustynka 1 PV farm and the construction of a double-circuit high-voltage cable power network 2x110kV with optical fibers, cable structure HV and accompanying infrastructure.