This is the third time that we carry out modernization works at this station. The first time we equipped the station with a telemechanics system – 2008. During the works in 2011, we installed an automatic voltage regulator 20 / 20kV imported by us from the United States.
The current scope of work to be carried out included the:
- delivery of HV and MV equipment, foundations and structures,
- construction of a second 110kV switching station,
- construction of TR2, TR1 stations,
- construction of teletechnical sewage system,
- construction of a 20kV busbar bridge,
- construction of a TRU1, TRU2 station,
- modernization of MV bays (TRU1 TRU2 i TR1 TR2),
- 110kV line overvoltage with insulation replacement,
- disassembly of old equipment of 110kV switching station,
- delivery, assembly and commissioning of auxiliary cabinets,
- delivery, assembly and commissioning of FR security cabinets,
- execution of the technical protection system,
- construction of area lighting, fibre optic lines and lightning protection system,
- execution of sanitary installations,
- construction of roads and station fencing,
- post-completion documentation.