The Elmont Grup is implementing another project related to photovoltaics. For the purposes of connecting the Augustynka 1 photovoltaic power plant with a capacity of 25 MW, we prepare technical documentation together with obtaining the necessary formal and legal decisions. Next, we will carry out construction and assembly works related to the construction of a 110 kV switching station and a through connection of the existing 110 kV Milejczyce – Adamowo line to the planned new 110 kV switching station.
Completion of the implementation is planned for the end of 2023.